Typical here: final council action around Mon, Mar 22, 2027 (about 20 weeks), and by Mon, Sep 13, 2027 for 80% of past cases. From 64 cases on this board's agendas since Tue, Jan 19, 2021, counted from the P&Z hearing on Mon, Dec 7, 2026.
Best case (calendar): about 6 weeks
- Fri, Oct 30, 2026 Submit applicationest. · no published deadline; assumes 30 days before P&Z
- Mon, Dec 7, 2026 P&Z hearing
- Mon, Dec 14, 2026 Council / Board vote
If P&Z continues it once: about 10 weeks (final vote Mon, Jan 11, 2027)
Agendas since Tue, Jan 19, 2021, here: 127 of 167 P&Z cases (76%) were on more than one P&Z agenda; first P&Z to final council action took 105 days at the median, 280 days for 80% of cases (64 cases).
Agendas since Tue, Jan 19, 2021, all tracked boards: 138 of 344 P&Z cases (40%) were on more than one P&Z agenda; first P&Z to final council action took 98 days at the median, 188 days for 80% of cases (80 cases).
No published submittal deadline, so this assumes filing 30 days before the P&Z meeting. Confirm with staff.
Built from published deadlines and meetings plus the code's rules. Doesn't count pre-application meetings or staff resubmittal rounds.
Set the filing date in Details to track this project's own schedule and log delays.